Entry name:Leachate Treatment Station of Lianyungang Municipal Solid Waste Landfill
Project location:Lianyungang Haizhou District Shisong Highway Domestic Garbage Landfill
Operation mode:Equipment procurement (including operation services)
Technology:Preprocessing + two-stage DTRO
The landfill site has been sealed, and the landfill leachate stored in the reservoir area is mainly treated. The daily inflow of this equipment is 55 cubic meters, and the water production is 37 cubic meters. The system recovery rate is controlled at about 70%, and the water production meets the discharge standard in Table 2 of Domestic Waste Landfill Pollution Control Standard (GB16889-2008). The produced water will be discharged to the urban sewage pipe network after reaching the standard.
1. Prepared technical solutions;
2. Design process drawings;
3. On-site technical guidance;
4. Research and development of process materials.
1. Prepared electrical design scheme;
2. Wrote application control programs;
3. Design electrical automatic control drawings;
4. Electrical construction wiring debugging.
1. Prepared technical solutions;
2. Design process drawings;
3. On-site technical guidance;
4. Research and development of process materials.
1. Prepared mechanical design scheme;
2. Design 3D manufacturing drawings;
3. Machining drawing, mechanical design;
4. 3D design of site construction.
1. Prepare electrical design scheme
2. Write application control program;
3. Design electrical control drawings;
4. Electrical construction wiring debugging